Key Takeaways
- Hoover Dam was constructed between 1931 and 1936, taking 5 years to complete ahead of schedule.
- The dam required 3,250,000 cubic yards of concrete, equivalent to a 2-lane highway from San Francisco to New York City.
- Over 21,000 workers were employed at peak construction, with a workforce averaging 5,251 men daily.
- The dam's base is 660 feet thick, tapering to 45 feet at the crest.
- Hoover Dam's crest length is 1,244 feet (379 meters) across the top.
- The structural height from riverbed to crest is 726.4 feet (221.3 meters).
- The Hoover Dam generates up to 2,080 megawatts of power.
- Annual energy production averages 4.2 billion kilowatt-hours.
- Seventeen main turbines produce 680 MW each in the Nevada wing.
- Lake Mead holds 28.23 million acre-feet at capacity.
- Maximum water surface elevation is 1,229 feet above MSL.
- Minimum power pool elevation is 1,050 feet.
- Hoover Dam cost $49 million to build, repaid by power revenues by 1987.
- Annual power revenues average $150 million since 2000.
- The dam enabled $1 trillion in economic activity since 1936.
Hoover Dam was a massive engineering project completed ahead of schedule during the Great Depression.
Construction History
- Hoover Dam was constructed between 1931 and 1936, taking 5 years to complete ahead of schedule.
- The dam required 3,250,000 cubic yards of concrete, equivalent to a 2-lane highway from San Francisco to New York City.
- Over 21,000 workers were employed at peak construction, with a workforce averaging 5,251 men daily.
- Construction cost $49 million in 1935 dollars, equivalent to about $1.1 billion in 2023 adjusted dollars.
- The Hoover Dam project was authorized by the Boulder Canyon Project Act of 1928 signed by President Coolidge.
- Six companies formed the Six Companies, Inc. consortium that won the bid to build the dam for $48.8 million.
- Diversion tunnels during construction totaled 15,000 feet in length, with diameters of 56 feet.
- Cooling coils totaling 582 miles were embedded in the concrete to control heat from curing.
- The first concrete was poured on June 6, 1933, and the last on May 29, 1935.
- High scalers removed 1.2 million cubic yards of sandstone from the canyon walls using jackhammers.
- 96 workers died during construction, with the last fatality on December 20, 1935.
- The upstream face was completed first on March 1, 1935, followed by the downstream face.
- President Franklin D. Roosevelt dedicated the dam on September 30, 1935.
- The dam was initially called Boulder Dam, renamed Hoover Dam in 1947 by President Truman.
- Cableways spanning 650 feet transported materials, each capable of lifting 20 tons.
- 4.4 million cubic yards of rock and earth were excavated for the foundation.
- The project generated over 3.5 million man-hours of labor during construction.
- Refrigeration plants produced aggregate chilled to 32°F for concrete mixing.
- The dam's construction halted the Colorado River flow for the first time in history.
- Black Canyon site was selected over Boulder Canyon due to better foundation rock.
- Initial workforce lived in Ragtown shantytown before Boulder City was built.
- Boulder City was constructed as a model city for 5,000 workers and families.
- The dam used 19.6 million pounds of structural steel and 300 miles of pipe.
- First power was generated October 9, 1936, with full capacity by 1947.
- The Colorado River Aqueduct construction paralleled the dam project.
- Hoover Dam's design is an arch-gravity type, pioneered by U.S. engineers.
- The project was completed under budget by $5 million.
- 2,000 miles of two-wire line telephone system supported construction communications.
Construction History Interpretation
Economic and Visitor Stats
- Hoover Dam cost $49 million to build, repaid by power revenues by 1987.
- Annual power revenues average $150 million since 2000.
- The dam enabled $1 trillion in economic activity since 1936.
- Boulder City population grew to 15,000 due to dam workers.
- Visitor center attracts 1 million tourists annually pre-COVID.
- Dam tours generate $10 million in fees yearly.
- Power allocations worth $4 billion annually to users.
- Construction paid $66 million in wages over 5 years.
- Lake Mead recreation contributes $1.5 billion to economy yearly.
- Dam supports 40,000 jobs in water and power sectors.
- Visitor numbers peaked at 1.7 million in 2015.
- The project irrigated 2 million acres of farmland.
- Power enabled aluminum production during WWII.
- Annual tourism spend at dam site is $400 million.
- Dam bonds repaid with interest totaling $56 million by 1952.
- Hoover Dam is a National Historic Landmark since 1984.
- Skywalk at nearby Bridge adds $30 million tourism revenue.
- Dam maintenance costs $50 million annually.
- Water deliveries valued at $500 million yearly for agriculture.
- The dam boosted GDP by 0.5% during Great Depression.
- 7 million visitors since tour center opened in 1983.
Economic and Visitor Stats Interpretation
Power Production
- The Hoover Dam generates up to 2,080 megawatts of power.
- Annual energy production averages 4.2 billion kilowatt-hours.
- Seventeen main turbines produce 680 MW each in the Nevada wing.
- Nine turbines in the Arizona wing generate 130 MW each.
- Power is distributed to Arizona, California, and Nevada.
- First generator went online August 20, 1939.
- Turbines have a head of 530 feet and flow of 68,000 cfs max.
- Annual revenue from power sales exceeds $100 million.
- The dam supplies 28% of Nevada's total power needs.
- Penstocks are 30 feet diameter steel pipes, 500 feet long.
- Station service units provide 15 MW for plant operations.
- Power plant capacity was upgraded in 1987 to 2,080 MW.
- Generators weigh up to 2.4 million pounds each.
- Annual output powers 1.3 million homes.
- Voltage step-up transformers raise output to 345 kV.
- The plant has 61 single-speed elevators for maintenance.
- Francis-type turbines rotate at 180 RPM.
- Powerplant elevation is 1,000 feet above sea level.
- Emergency generators provide 2.4 MW backup.
- Hoover Dam power fueled Las Vegas' growth post-WWII.
Power Production Interpretation
Structural Dimensions
- The dam's base is 660 feet thick, tapering to 45 feet at the crest.
- Hoover Dam's crest length is 1,244 feet (379 meters) across the top.
- The structural height from riverbed to crest is 726.4 feet (221.3 meters).
- Hydraulic height of the dam is 714 feet (218 meters).
- Crest width averages 45 feet (14 meters), with 8-foot-wide roadway.
- The dam contains 3,250,000 cubic yards (2.5 million m³) of concrete.
- Upstream face radius curves with a 640-foot (200 m) radius.
- Downstream face has a 700-foot (210 m) radius at the base.
- The dam weighs approximately 6.6 million tons.
- Spillway elevations are at 1,176 feet above sea level.
- Power plant wings extend 670 feet upstream from the dam.
- Intake towers rise 395 feet above the riverbed.
- The dam's foundation is embedded 10 feet into bedrock.
- Crest elevation is 1,232 feet above mean sea level.
- Riverbed elevation at dam site is 505 feet above sea level.
- The dam is 660 feet wide at the base.
- Elevator shafts descend 716 feet inside the dam.
- Four government columns on the Arizona side are 30 feet square.
- Wing walls are 520 feet long on the Nevada side.
- The Angel of the River statues are 30 feet high.
- Terrace No. 1 supports the intake towers, spanning 500 feet.
- The dam's profile is a parabolic arch design.
- Concrete blocks were poured in 5-foot lifts, each 50x50x5 ft.
Structural Dimensions Interpretation
Water Storage and Flow
- Lake Mead holds 28.23 million acre-feet at capacity.
- Maximum water surface elevation is 1,229 feet above MSL.
- Minimum power pool elevation is 1,050 feet.
- Average annual inflow is 10 million acre-feet.
- Diversion tunnels carry 200,000 cfs during floods.
- Lake Mead covers 247 square miles at full pool.
- Hoover Dam supplies water to 25 million people via aqueducts.
- Annual water releases average 9 million acre-feet.
- Spillway stilling basins are 50 feet deep.
- Colorado River flow at dam averages 15,000 cfs.
- Lake Mead dead pool is 895 feet elevation.
- Irrigation deliveries total 1.5 million acre-feet yearly to Arizona.
- The dam controls floods protecting 1 million acres downstream.
- Water temperature is cooled to 55°F before release.
- Central Arizona Project receives 1.6 million acre-feet annually.
- Lake Mead shoreline extends 550 miles.
- Maximum depth of Lake Mead is 532 feet.
- Sediment trap capacity is 1.25 million acre-feet.
- River outflow regulated to 10,000 cfs minimum.
- Hoover Dam provides 90% of Southern Nevada's water.
- Historical low elevation was 1,068 feet in 2022.
- The dam created Lake Mead, largest U.S. reservoir by volume.
- Evaporation losses average 700,000 acre-feet per year.
- Bypass tubes in intakes prevent cavitation damage.
Water Storage and Flow Interpretation
Sources & References
- Reference 1USBRusbr.govVisit source
- Reference 2ENen.wikipedia.orgVisit source
- Reference 3NPSnps.govVisit source
- Reference 4HISTORYhistory.comVisit source
- Reference 5ENGINEERINGengineering.comVisit source
- Reference 6PBSpbs.orgVisit source
- Reference 7SIsi.eduVisit source
- Reference 8ASCEasce.orgVisit source
- Reference 9WATERDATAwaterdata.usgs.govVisit source
- Reference 10BRITANNICAbritannica.comVisit source
- Reference 11LVVWDlvvwd.comVisit source
- Reference 12DOIdoi.govVisit source
- Reference 13POWER-TECHNOLOGYpower-technology.comVisit source
- Reference 14REVIEWJOURNALreviewjournal.comVisit source
- Reference 15LAKEMEADNATIONALRECREATIONAREAlakemeadnationalrecreationarea.comVisit source
- Reference 16USGSusgs.govVisit source
- Reference 17BOULDERCITYbouldercity.comVisit source
- Reference 18ENERGYenergy.govVisit source
- Reference 19HISTORYhistory.navy.milVisit source
- Reference 20LASVEGASADVISORlasvegasadvisor.comVisit source
- Reference 21HOOVERSKYWALKhooverskywalk.comVisit source
- Reference 22FRASERINSTITUTEfraserinstitute.orgVisit source






